Progress Report
Generates the project progress report with blockers and next steps. Use for the customer or management.
Pack: Projects & TasksProcedure
- 1Collect tasks by status: done, in progress, to start
- 2Compute percent progress on completed tasks
- 3List blockers with cause and who must unblock
- 4Define the 3 next steps with owner and date
- 5Flag deviations from plan
Rules
- · Progress is computed on tasks, not effort estimates
- · No blocker without an assigned owner
- · If a project date slips, state it: never 'on track' when it is not
Expected output
Report: % progress + done/in-progress/to-start + blockers (cause, owner) + 3 next steps
When not to use it
- · Project without tracked tasks: the report would be invented
- · Internal and external use together: ask which
Example requests
«Where are we with the catalog project?»